The aircraft has been delivered, painted, registered and parked on its stand, and nobody is allowed to sell a seat on it. The scene is replayed with every new operator, and it surprises above all those who come from finance or from industry rather than from operations. What sets the date is almost never fleet availability: it is an organisation’s ability to describe itself in writing, to have those who lead it accepted, and then to show itself in operation before its authority. Here is where the time really goes, and why the schedule announced at the press conference almost always slips in the same direction.
The schedule does not begin at delivery
The course of an initial certification goes by different names depending on the authority, but its logic is everywhere the same: a pre-application contact that frames the scope requested, a formal application that officially opens the file, a documentary review, a demonstration phase, then the decision. Only the first step is entirely in the applicant’s hands. From the formal submission onwards, the pace becomes that of an exchange: the operator sends, the authority reads and replies, and the real lead time is measured in the number of round trips, not in the volume produced.
Two files advance in parallel and do not overlap. The air operator certificate answers the technical question: is this organisation capable of safely conducting the type of operation requested. The operating licence answers an economic and legal question: financial fitness established on a documented business plan, insurance cover taken out, ownership and control structure in compliance. In practice the two are issued together, and the classic mistake is to mobilise the whole team on the first one, only to discover late that the second requires effective financial commitments, and therefore cash tied up, before the first revenue is even earned.
The scope requested also drives the duration. Every specific approval sought from the outset, whether low visibility operations, performance-based navigation, extended diversion time operations or the carriage of dangerous goods, adds its own set of procedures, its training programme, its qualification criteria and, often, its own demonstration. An airline that asks for everything on day one does not save time: it stacks independent critical paths on the same small team.
The certification process is like a relay race: each step depends on the previous one being completed correctly. The biggest delays happen during the “review loops,” where the authority and operator exchange documents back and forth. The more complete and accurate your first submission, the faster this process goes.
A new airline in Europe requested approval for low-visibility operations, performance-based navigation, and dangerous goods carriage from day one. Their certification process took 18 months instead of the expected 12 because each additional approval required its own set of procedures, training programs, and demonstrations. A more focused initial scope could have saved 6 months.
Nominated persons: the first gate, and the narrowest
An operator presents itself to its authority with an accountable manager, who commits the company and genuinely has the resources at hand, and a set of nominated persons covering flight operations, ground operations, crew training and continuing airworthiness. To these are added the safety management and compliance monitoring functions, whose independence from operations is examined closely. The authority does not merely read career histories: it interviews these people, checks that they know the manual they have signed and that they can describe, without reading it, the process for which they answer.
Three difficulties come up systematically. Availability first: the chosen candidate is almost always in post elsewhere, with a notice period, and acceptance only holds for someone who actually performs the function. Then the combining of roles: a fledgling structure wants to concentrate several areas on the same person, which remains conceivable for a modest operation but requires demonstrating that the workload is sustainable and that compliance monitoring is not checking its own work. Replacement, finally: changing a nominated person during the process restarts acceptance for that area and, often, the review of the chapters they owned.
| Criterion | Full-time recruitment | Experienced contractor, shared time |
|---|---|---|
| Time to take up the post | Long: notice period, often several months | Short: available within a few weeks |
| Acceptance by the authority | Single interview, straightforward file | Questions about the combined workload and other mandates |
| Ownership of the manuals | Writes what they will apply themselves | Brings proven texts, less rooted in the company |
| Cost during the revenue-free phase | Full salary long before the first flight | Split, adjustable to the pace of the file |
| Risk during ramp-up | Low: the person stays | High: departure creates a vacancy in an accepted post |
| Effect on initial oversight | Stable point of contact, memory of the file | Handover to be planned and documented |
In practice the choice is not binary: many applications combine a salaried core on flight operations and airworthiness with external support on compliance for the duration of the certification. What matters is that the arrangement is announced at the pre-application contact and not discovered by the authority at interview time.
The manuals: the chain of dependencies that sets everything else
The operations manual is not a document, it is the written mirror of an organisation, and its parts cannot be drafted in any order. The general part follows from the safety policy, the management system and the organisation chart, and therefore from the persons accepted. The aircraft part follows from the flight manual and the manufacturer’s master minimum equipment list, from which the list applicable to the fleet is derived. The route part follows from the aerodromes selected, their categorisation and the associated minima. The training part follows from everything above, since one does not train on procedures that are not yet frozen.
Think of the operations manual like a house of cards. If you change one card (like your route network), the whole structure shifts. That’s why you can’t finish one section before the others are ready. Every change ripples through the entire manual, creating more work.
An airline in Africa changed their cabin configuration 3 months before their first flight. This small change required updates to their training manual (new procedures for crew), their equipment list (new equipment needed), and their minima (new weight and balance calculations). What should have been a 1-page change turned into 30 pages of revisions, delaying their certification by 2 months.
To this set are added the continuing airworthiness management exposition, the maintenance programme, the contracts with the maintenance organisation, the security programme and the emergency response plan. Each refers to the others, and version control becomes the real job. A manual under review is a moving target: the authority reads a dated state, the operator keeps correcting, and without revision discipline the two parties end up discussing different texts. Files that move quickly freeze a reference version, amend it only through numbered revisions carrying change marks in the margin, and keep a log stating for each revision what it changes and which finding it closes. The corollary is counter-intuitive: correcting too quickly, on the fly, slows the file down, because the inspector has to re-read what they had already accepted.
The right reflex: build the compliance matrix before writing the first page of any manual. One line per applicable requirement, one column for the manual paragraph that addresses it, one for the associated evidence, one for the progress status. This matrix is what the authority will use to process the file; providing it complete at submission eliminates the first review loop, the one spent looking for where each subject has been dealt with.
The trap: the manual taken over from another operator. It is spotted within minutes, because it describes an organisation that is not yours: posts that do not exist in the organisation chart filed, references to aircraft types absent from the fleet, procedures built around a different network, forms bearing a reference foreign to the declared documentation system. The cost is not only correction time: the file loses the benefit of the doubt, and the next review becomes exhaustive instead of targeted.
The demonstration: what the authority actually comes to check
Demonstration flights do not validate the aircraft. It is certified, it holds its certificate of airworthiness and its airworthiness review certificate, and it is maintained by an approved organisation. What the inspection observes is the complete chain around the flight: preparation, the flight file, the mass and balance calculation, the operational decision in degraded weather, the handling of an item deferred on the minimum equipment list, the transmission of documents, the post-flight report and the way it feeds back into the safety management system. The flight deck is only one of the observation points; the flight preparation office and the technical department are others.
Part of the demonstration takes place on the ground and without an aircraft: an emergency response plan exercise on an imposed scenario, review of the cabin crew training programmes including evacuation and survival drills, verification of the security arrangements, of dangerous goods handling and of training traceability. These exercises reveal what no manual shows: whether the people know one another, whether the call-out numbers are up to date, whether someone knows who decides in the middle of the night.
The demonstration phase is like a game of whack-a-mole. Every time the inspectors find an issue, you have to fix it, update your manuals, and then show them again. The more issues they find, the more loops you have to go through, and the longer it takes.
A European airline had to repeat their emergency response plan exercise 3 times. First, they didn’t have all the right people present. Then, their call-out procedures were too slow. Finally, they had to prove they could handle a real emergency scenario. Each repeat added 2 weeks to their schedule, making their certification take 6 months longer than planned.
The content of this phase varies greatly with the type of operation, something that schedules copied from one project to another ignore. An all-cargo operation dispenses with cabin evacuation drills, but sees load restraint, load planning, dangerous goods handling and the interface with handling agents that are not its own move to the foreground. An on-demand operation demonstrates its ability to prepare for an aerodrome it has never served, with an aerodrome assessment carried out within the week, whereas a scheduled network demonstrates repeatability at familiar stations. And an operator flying under contract for a principal must in addition show that its own procedures prevail over its customer’s commercial instructions. Two files with the same fleet can therefore diverge very widely on this single point, and the explanatory variable is almost always the quality of the first documentary submission.
The paradox of line training for the first crews
Here is the knot that new entrants often discover too late. Line flying under supervision requires real flights, and commercial flights require the certificate. The knot is untied in two ways: the demonstration flights themselves, which can carry part of the first crews’ line experience, and the borrowing of instructors, seconded from another operator or from an approved training organisation, whose acceptance is a milestone in its own right. That arrangement is negotiated months in advance, because available instructors are scarce and their home operator has no interest in lending them out in high season.
The trap: qualifying crews too early. Type conversion course, security training, dangerous goods training, recency, medical fitness: each of these boxes opens a validity window that starts running from its completion, not from the first commercial flight. A course trained too far in advance will have to repeat part of the programme, and that catch-up falls exactly when the organisation is at its most stretched, with the same instructors and the same simulator already booked for the next course.
The critical path, item by item
A start-up operator’s schedule reads like any other plan: some items carry the lead time, others have float. What misleads is that the most visible items, the ones the press talks about, are precisely those with float.

| Item | Depends on | Position | What derails it |
|---|---|---|---|
| Aircraft and airworthiness | Manufacturer or lessor, continuing airworthiness management organisation | Rarely critical | Transfer of responsibilities between States, registration, paint delay |
| Nominated persons | Labour market, the authority’s interview diary | Critical from the outset | Notice periods, refusal, departure during the process |
| Manuals and compliance matrix | Almost everything else | Critical, and the longest | Number of review loops |
| Crew training | Approved manuals, accepted instructors, simulator slots | Critical at the end of the path | Validities expiring, simulator saturated |
| Specific approvals | Scope chosen at the pre-application contact | Critical if everything is requested at once | Additional procedures and demonstrations |
| Operating licence and insurance | Business plan, insurance market | Parallel, blocking at the finish | Financial fitness to be demonstrated again if the schedule slips |
| Slots, stations, ground handling | Commercial, airport coordination | Rarely critical | Seasonality: a missed launch pushes back by a whole season |
The last row deserves a pause, because it explains how brutal some postponements are. A launch missed by three weeks is not a three-week postponement: if the season turns, the network, the fleet and the planned headcount no longer make commercial sense, and the operator finds itself carrying a complete structure through several months of trough. It is this mechanism, and not the cost of the certification process itself, that carries off most of the projects that never make it.
What to check before committing to a date
If you are handling an application, three checks are worth more than an optimistic schedule. The first: does the compliance matrix point to paragraphs that genuinely exist in the version of the manuals filed, and not to a provisional numbering. The second: can each nominated person describe their process without opening the binder, and above all, can they say what they do when that process fails. The third: was the demonstration programme discussed with the authority before being written, or discovered by them on reading.
If you are approached to join a new entrant, the useful question is not the date announced but the state of the application. Has the formal application been filed. Are the nominated persons accepted, or only recruited. Is the manual on its first or its third review. Are the instructors identified and their secondment under contract. Are the simulator slots booked. Four precise answers out of five point to an organisation that knows where it stands; four approximations point to a schedule that exists only in a presentation. The date of the type rating, for its part, is negotiable: a type conversion positioned late with a contract that provides for it is worth more than a rating granted early and recency lost before the first rotation. This is a point to raise at interview, in the same way as the preparation for the type rating itself.
One grey area remains, and it must be named: the authority’s workload. No text guarantees a processing time, and the number of inspectors available for an initial certification depends on an oversight plan that covers existing operators first. An impeccable application filed at the wrong time of year waits. That is a further argument for discussing the initial scope: a certificate issued for a narrow operation, then extended by amendment once continuing oversight is under way, almost always opens earlier than a complete application from the outset. The profiles capable of sustaining these short, intense phases move around a great deal between projects, and are often recruited for an independent assignment rather than on a permanent contract.
This text describes a general mechanism and replaces nothing: the applicable regulation, the decisions and guidance of your supervisory authority and the operator’s approved documentation prevail over everything above, both where they differ and where they are silent.
Questions fréquentes
Are the air operator certificate and the operating licence processed separately?
They are two distinct files, processed in parallel and in practice issued together, but they do not answer the same question. The certificate concerns the technical ability to operate the requested scope safely; the licence concerns financial fitness, insurance and the ownership and control structure. The classic mistake is to concentrate the whole team on the first and to discover late that the second requires effective financial commitments before the first revenue. If the schedule slips, financial fitness often has to be demonstrated again on more recent accounts.
How long does the manual review actually take?
No lead time is guaranteed, and the duration is measured in the number of round trips rather than in weeks. A file delivered with a complete compliance matrix and accurate cross-references eliminates the first loop, the one that serves only to locate the subjects. A manual taken over from another operator, on the contrary, adds several, because the review becomes exhaustive.
Can a nominated person covering several areas be accepted?
Yes, it is common in a modest operation, but the combination has to be demonstrated. It must be established that the workload is sustainable, that the competences cover each area and that compliance monitoring keeps its independence from the activities it controls. The arrangement must be announced at the pre-application contact, not discovered during the interviews.
How do the first crews gain their line experience before the certificate is issued?
Through two complementary routes. The demonstration flights can carry part of that experience, under supervision and according to a programme agreed with the authority. And the operator has instructors accepted who are seconded from another operator or from an approved training organisation. That secondment is negotiated well in advance, because available instructors are scarce in high season.
Is it better to request all the specific approvals at initial certification?
Rarely. Each approval adds its procedures, its training programme, its qualification criteria and often its own demonstration, on a team that remains small. A narrow initial scope, then extended by amendment once continuing oversight is under way, generally opens earlier. The only exception concerns approvals without which the planned network does not hold together.
What should you ask a new entrant before accepting a job with it?
Five factual points: has the formal application been filed, are the nominated persons accepted or only recruited, which review round have the manuals reached, are the instructors under contract, are the simulator slots booked. You should also negotiate the positioning of your own rating, because a type conversion obtained too early sees its recency expire before the first rotation.